Bitdeer Announces January 2026 Production and Operations Update

      Monthly Highlights
      Increased self-mining hashrate to 63.2 EH/s on continued deployment of SEALMINERs
      Bitcoin production increased 430% year over year to 668 Bitcoin
      Launch of NVIDIA GB200 NVL72 infrastructure in Malaysia
      First design of Litecoin chip taped out and initial testing surpassed expectations
        
SINGAPORE, Feb. 10, 2026 (GLOBE NEWSWIRE) — Bitdeer Technologies Group (NASDAQ:BTDR) (“Bitdeer” or the “Company“), a world-leading technology company for Bitcoin mining and AI infrastructure, today announced its unaudited mining and operations updates for January 2026.

Operational Update

  • Self-mining: 
    • Mined 668 Bitcoins, an increase of approximately 430% year over year.
    • Self-mining hashrate reached 63.2 EH/s.
    • Bitdeer will continue deploying SEALMINER mining rigs for self-mining to continue the Company’s growth in self-mining capacity while concurrently retiring third-party, older-generation rigs.
  • SEALMINER Manufacturing:
Mining Rig Model (EH/s) Stage January 2026 December 2025
SEALMINER A3 In final assembly 3.8 0.6
  In transit 0.4 2.5
  Cumulative A3 Deployed 8.7 5.9
SEALMINER A2 In final assembly 2.9 1.8
  Ready for shipping 0.1 0.1
  In transit 2.6 3.4
  Cumulative A2 external sales 8.1 7.9
  Cumulative A2 Deployed 44.1 39.7
SEALMINER A1 Cumulative A1 Deployed 4.2 4.2
3rd Party Miners Cumulative Deployed 8.1 8.2
Total Proprietary Hash Rate Deployed 65.1 58.0
  • SEALMINER R&D:
    • Successfully taped out the Litecoin ASIC chip, SEAL-DL1, designed for mining DOGE and Litecoin. Initial test results of SEAL-DL1 have exceeded expectations.
    • SEALMINER DL1 is expected to generate more mining output compared to the SEALMINER A2 series with the same power capacity based on the recent market parameters. We plan to launch the product in Q1 2026.
    • SEALMINER 04-1 is targeting mass production in Q1 2026.
    • SEAL04-2 chip’s development continues.
  • U.S. Manufacturing: Preparations for Bitdeer’s U.S. factory are progressing, with the lease signed and construction permit application submitted to local municipal authorities.
  • GPU Cloud as of 1/31/2026:
GPU Amount Deployed GPU Types Utilization Rate Under External Subscription ARR
1,792 H100, H200, B200, GB200 41% 585 ~$10 million
    • On January 13, 2026, Bitdeer AI deployed its initial NVIDIA GB200 NVL72 infrastructure in Malaysia, marking the first phase of an accelerated capacity expansion designed to support enterprise-grade training workloads on the Blackwell architecture.
    • Actively evaluating U.S. data center leasing opportunities to deploy GPUs and bring AI cloud services online for U.S. customers as early as Q1 2026.
  • HPC colocation arrangements:
    • Potential colocation arrangements for various sites are under evaluation. Multiple potential hyperscaler customers have expressed strong interest, and active discussions are currently underway.
  • Infrastructure Summary:
Site / Location Capacity (MW) Status Datacenter Type Timing1
Electrical capacity        
– Rockdale, Texas

Full story available on Benzinga.com